Electricity Disputes Tribunal - 2021 March

2 judgments
  • Filters
  • Judges
  • Alphabet
Sort by:
2 judgments
Citation
Judgment date
March 2021
Complainant failed to prove ownership or entitlement to compensation; respondent had lawfully identified and compensated other PAPs.
Compensation for land – proof of ownership and possession – weight of documentary and oral evidence – identification and compensation of Project Affected Persons under a Resettlement Action Plan – burden on claimant to prove entitlement – costs awarded to successful respondent.
26 March 2021
Complainants awarded compensation for crops and trees destroyed by state power-line works; land compensation limited to transformer sites.
Electricity infrastructure — wayleaves and compensation — entitlement to compensation for destroyed crops and trees; land not ordinarily compensable under 33kV/low-voltage projects except where transformers or underground earthings are located — contemporaneous Wayleaves assessment forms as primary evidence of loss — claims for houses require clear proof; interest and costs awarded.
18 March 2021