A licensee’s failure to restore electricity for two years was negligent, warranting general damages though service fees were lawful.
Electricity law – statutory duty to supply – negligence for failure to restore supply; evidence must be consistent with pleadings; service/access charges lawful under s.78; special damages must be specifically pleaded and proved; general damages discretionary.
4 February 2015