Electricity Disputes Tribunal - 2015 December

1 judgment
  • Filters
  • Judges
  • Alphabet
Sort by:
1 judgment
Citation
Judgment date
December 2015
Unjustified safety disconnection and undocumented delayed reconnection warranted limited special damages, general damages and costs.
Electricity law – Disconnection for safety – Licensee must demonstrate dangerous condition and follow Primary Grid Code/Quality of Service Code procedures; notice and investigatory records required; unlawful disconnection and unreasonable delay in reconnection may attract general and proved special damages.
21 December 2015