A complaint filed by a non-existent entity lacks capacity and is a nullity that must be struck out.
Electricity Disputes Tribunal – parties and pleadings – substitution/amendment of parties – capacity to sue – non-existent plaintiff – nullity of proceedings – O.6 r.19 CPR v O.1 r.10 CPR – tribunal’s discretion to dispense with procedural formality but cannot cure substantive defect.
21 October 2015
Tribunal ordered interim reconnection on phased payments balancing theft prevention and the complainant’s hardship.
Electricity disputes – interim reconnection pending determination – balancing utility’s duty to prevent power theft with consumer hardship; partial/phased payment as condition for reconnection; refund or credit of interim payments if claimant succeeds; right to disconnect on default.