Part I – Interpretation
1. Interpretation
In this Act, unless the context otherwise requires—“appointed officer” means a person appointed under section 10(1);“assessment officer” means a public officer or other person appointed by the Minister to be an assessment officer for the purposes of this Act, either generally or in a particular case;“currency point” has the value assigned to it in the Schedule to this Act;“declaration” means a declaration made under section 3(1);“person having an interest” in relation to any land includes all persons claiming an interest in compensation payable for or in respect of the land under this Act and all persons having an interest in an easement affecting the land;“registered proprietor” in relation to land means a person registered as proprietor of the land under the Registration of Titles Act;“Register Book” means the Register Book kept in pursuance of the Registration of Titles Act.Part II – Acquisitions, etc.
2. Power to enter on and examine land
3. Declaration that land is needed for public purpose
4. Land to be marked out, eta
On the publication of a declaration under section 3 in respect of any land, the assessment officer shall cause the land to be marked out and measured and a plan of the land to be made if a plan of the land has not already been made.5. Notice to persons having an interest
6. Inquiry and award
7. Taking possession
8. Withdrawal from acquisition
9. Acquisition of part of house, manufactory or other building
10. Temporary occupation of waste or arable land for public purpose
11. End of temporary occupation
12. Power of Minister where claim for severance is excessive
Part III – Legal proceedings
13. Appeals
Where an award is made under section 6, any person awarded or claiming that he or she should have been awarded compensation may within sixty days from the date of the award appeal to the High Court by way of objection to any or all of the following—14. References to court
15. Enforcement of right to possession
16. Rules on procedure, etc.
Part IV – Miscellaneous
17. Offences and penalties
Any person who—18. Service of notices, etc.
Without prejudice to any other method of service, any notice, declaration or similar document required to be served for the purposes of this Act may be served by post or, if it relates to land or premises and it is not practicable after using due diligence to serve it on the person on whom it should be served, by delivering it to some person on the land or premises to which it relates or, if there is no person on the land or premises to whom it can be delivered, by affixing it or a copy of it to some conspicuous part of the land or premises.19. Saving for acquisition by agreement, etc.
Nothing in this Act shall prevent the Government from entering into an agreement with a person having an interest in land by which—20. Regulations
The Minister may, by statutory instrument, make regulations for the assessment and payment of compensation under this Act and generally for giving full effect to the provisions and purposes of this Act.21. Power to amend Schedule
The Minister responsible for finance may, by statutory instrument, with the approval of Cabinet, amend the Schedule to this Act.History of this document
31 December 2023 this version
Consolidation
28 July 2023
31 December 2000
Consolidation
Read this version
02 July 1965
Commenced
Cited documents 0
Documents citing this one 4
Gazette 2
1. | Uganda Government Gazette dated 2001-12-17 number 81 | |
2. | Uganda Government Gazette dated 2003-10-03 number 46 |
Judgment 1
1. | Registered Trustees of Kampala Institute v Departed Asians Property Board [1994] UGSC 18 (1 August 1994) |
Ordinance 1
1. | Game (Preservation and Control) Act |
Subsidiary legislation
Title
|
Date
|
|
---|---|---|
Land Acquisition (East African Crude Oil Pipeline) Instrument, 2019 | Statutory Instrument 105 of 2019 | 29 November 2019 |